Windhoek Airport freeway, Phase 2A

PTS-SOlutions Watermark

The construction of the freeway between Windhoek and the Hosea Kutako International Airport had been earmarked since the mid-seventies. A route determination study was done in 1971, followed with a Basic Design and Report in 1978, the latter which still today forms the basis for the detail design of this freeway.

The project is sub-divided into 3 phases (Phases 1, 2A and 2B) because of the urgency Government has attached to the project,

The project is situated along Trunk Road 9 Section 1 between Windhoek and Hosea Kutako International Airport. It forms part of the third phase of the construction of Trunk Road 9 Section 1 to freeway standards.

Phase 2 covers the section between Sam Nujoma Interchange and east of the Hosea Kutako International Airport. Sub-phase 2A covers the section up to a point just east of the Kapps Farm Interchange over a distance of 19.5km, with Phase 2B covering 21.3km.

Scope:                          

PTS-S caried out the design, supply & installation of multi-strand bonded post tensioning for all the bridges on this phase of the project, which consisted of 6 bridges spread over 4 interchanges as follows:

  • Sam Nujoma interchange consisted of two 50m long bridge decks with 20No off 13-strand PT tendons
  • Klein Windhoek Interchange consisted of two 41m long bridge decks with 16No off 15-strand PT tendons
  • Otjihase Interchange consisting of a single 94m long bridge deck with 16No off 15-strand PT tendons
  • Kapps Farm Interchange consisting of a single 110m long bridge deck with 16No off 13-strand PT tendons

Project Data Sheet

Year

2022 - 2023

Location

Between Windhoek & Hosea Kutake International airport

Client

Namibian roads authority

Project Type

Civils

Scope

Phase 2B of the construction of the freeway between Windhoek and the Hosea Kutako International Airport